Trustees for the Time Being of the GroundWork Trust v. Minister of Environmental Affairs, KiPower (Pty) Ltd, and Others

Filing Date: 2017
Reporter Info: Case no. 54087/17
Status: Pending
Case Categories:
  • Suits against governments
    • Environmental assessment and permitting
      • Utilities
Jurisdictions:
  • South Africa
    • High Court
Principal Laws:
  • South Africa
    • National Environmental Management Act 107 of 1998
Summary:

The environmental organization groundWork has filed a motion requesting that South Africa’s High Court review and set aside the Department of Environmental Affair’s authorization to develop a 600 MW coal-fired power plant, the “KiPower Project,” without first considering the climate change impacts of the plant. They also challenge the Minister of Environmental Affairs’ decision to dismiss groundWork’s appeal of the authorization.

Petitioners argue this dismissal directly contradicts the Court’s decision in EarthLife Africa Johannesburg v. Minister of Environmental Affairs and Others handed down on March 8, 2017. This case considered similar authorization for a 1200 MW coal-fired plant called the Thabametsi Project. In EarthLife Africa Johannesburg, the Court held that “the climate change impacts of a proposed coal-fired power station are required to be assessed and comprehensively considered as part of an environmental impact assessment (“EIA”)” under the National Environmental Management Act 107 of 1998 before an authorization decision is reached. National Environmental Management Act Section 24O(1)(b) further requires consideration of impacts, mitigation measures, and domestic as well as international policy commitments before granting an environmental authorization. In EarthLife Africa Johannesburg, the Court recognized South Africa’s commitments under the Paris Agreement as one of the reasons that climate change is a relevant consideration for the environmental review of a coal-fired power plant. This case is one of two court applications filed by groundWork in September 2017 to oppose new coal-fired power plants in the Mpumalanga Highveld –an air quality priority area.

At Issue: Consideration of climate change in environmental impact statements
Case Documents:
Filing Date Type File Summary
09/05/2017 Petition Download No summary available.