In re River District Energy Limited Partnership

Reporter Info: [2011] Carswell BC 3538
Status: Certificate granted
Case Categories:
Jurisdictions:
  • Canada
    • British Columbia
      • Utilities Commission
Principal Laws:
  • Canada
    • Utilities Commission Act (British Columbia)
Summary:

British Columbia Utilities Commission granted a Certificate of Public Convenience and Necessity (CPCN) to River District Energy Limited Partnership (RDE), allowing RDE to construct and operate a District Energy Utility in southeast Vancouver. The project is found to serve the public interest and align with British Columbia’s energy objectives. The initial energy source will be natural gas; RDE plans to begin using waste heat generated by the Burnaby Waste to Energy Facility beginning in 2016. However, RDE is under no binding legal obligation to shift to a renewable energy source. The Commission is confident in the planned facility’s potential to reduce greenhouse gas emissions over its lifetime, despite a projected 40% increase in GHG emissions by RDE over the first four years of the project.

At Issue: Certificate of Public Convenience and Necessity sought
Case Documents:
Filing Date Type File Summary
12/19/2011 Decision Download No summary available.