Ålands Vindkraft AB v. Swedish Energy Agency

“Ålands Vindkraft AB v. Energimyndigheten”

Reporter Info: [2014] Case C-573/12
Status: Denied
Case Categories:
  • Suits against governments
    • Environmental assessment and permitting
      • Renewable projects
Jurisdictions:
  • European Union
    • European Court of Justice
Principal Laws:
  • European Union
    • Secondary Law
      • Directives
        • 2009/28/EC
Summary:

A Finnish wind farm challenged defendant Swedish energy agency’s refusal to grant a green electricity certificate. The agency refused on the grounds that only green electricity production installations located within the Swedish territory may be awarded the certificate. Plaintiff claimed that the territorial limitation of Sweden’s energy certificate scheme under Directive 2009/28 was inconsistent with Article 34 of the Treaty on the Functioning of the European Union (TFEU). The court upheld Sweden’s national support scheme and found that it was compatible with TFEU Article 34 because the national quota promotes increased use of renewable energy sources in electricity production.

At Issue: Challenge to Sweden's green energy certificate scheme
Case Documents:
Filing Date Type File Summary
07/01/2014 Judgment Download No summary available.

© 2023 · Sabin Center for Climate Change Law · U.S. Litigation Chart made in collaboration with Arnold & Porter Kaye Scholer LLP