Protect Our Parks, Inc. v. Buttigieg

Filing Date: 2021
Case Categories:
  • Federal Statutory Claims
    • Clean Water Act
  • Federal Statutory Claims
    • NEPA
  • Adaptation
    • Actions seeking adaptation measures
  • Federal Statutory Claims
    • Other Statutes and Regulations
Principal Laws:
National Environmental Policy Act (NEPA), National Historic Preservation Act (NHPA), Clean Water Act (CWA), Urban Park and Recreation Recovery Act, Department of Transportation Act (Section 4(f)), Rivers and Harbors Act
Description: Challenge to federal approvals for the construction of the Obama Presidential Center in Jackson Park in Chicago.
  • Protect Our Parks, Inc. v. Buttigieg
    Docket number(s): 21-2449
    Court/Admin Entity: 7th Cir.
    Case Documents:
    Filing Date Type File Action Taken Summary
    07/01/2022 Opinion Download Denial of motion for preliminary injunction affirmed.
    08/19/2021 Opinion Download Opinion issued explaining decision to deny motion to enjoin construction pending appeal.
  • Protect Our Parks, Inc. v. Buttigieg
    Docket number(s): 1:21-cv-02006
    Court/Admin Entity: N.D. Ill.
    Case Documents:
    Filing Date Type File Action Taken Summary
    03/29/2022 Opinion and Order Download Counts VI, VIII, IX, XI, XII, XIII, and XV dismissed with prejudice and Count VII dismissed without prejudice.
    08/12/2021 Memorandum Opinion and Order Download Memorandum opinion and order issued stating reasons for court's denial of motion for preliminary injunction.
    04/14/2021 Complaint Download Complaint filed. Challenge to Federal Approvals of Obama Presidential Center Alleged Violations in Connection with Modifications to Resilience Project. Two not-for-profit organizations and five individuals filed a lawsuit in the federal district court for the Northern District of Illinois asserting that federal approvals of the construction of the Obama Presidential Center in Jackson Park in Chicago failed to comply with “the letter and spirit” of federal statutes, including Section 4(f) of the Department of Transportation Act, Section 106 of the National Historic Preservation Act, the Urban Park and Recreation Recovery Act, and the National Environmental Policy Act. The plaintiffs’ allegations also included that the Obama Presidential Center would have significant and permanent impacts on the Great Lakes Fishery and Ecosystem Restoration Project at Jackson Park, a large project led by the U.S. Army Corps of Engineers and designed to address climate change’s impacts on the South Side of Chicago, among other environmental functions. The plaintiffs asserted that the Corps’ approval of modifications to the project violated the Rivers and Harbors Act and the Clean Water Act.