• Skip to main content
  • Home
  • Contact
  • About
  • Search
    • Search US
    • Search Global
  • Global Litigation
  • U.S. Litigation

Sierra Club v. Federal Energy Regulatory Commission

Filing Date: 2016
Case Categories:
  • Federal Statutory Claims
    • NEPA
Principal Laws:
National Environmental Policy Act (NEPA)
Description: Challenge to FERC approvals for natural gas pipeline from Alabama to Florida.
  • Sierra Club v. Federal Energy Regulatory Commission
    Docket number(s): 16-1329
    Court/Admin Entity: D.C. Cir.
    Case Documents:
    Filing Date Type File Action Taken Summary
    03/23/2018 Notice Download FERC notified D.C. Circuit that it had issued order on remand.
    03/14/2018 Order Download FERC issued order on remand. FERC Reauthorized Southeast Market Pipelines Project After D.C. Circuit Allowed FERC More Time to Complete Review on Remand. On March 14, the Federal Energy Regulatory Commission (FERC) issued an order reinstating the certificate of public convenience and necessity for the Southeast Market Pipelines Project. FERC said its quantification of downstream greenhouse gas emissions did not alter its conclusion that the project was an environmentally acceptable action. FERC’s supplemental environmental impact statement concluded that there was no way to determine the significance of the project’s emissions using either the social cost of carbon tool—which FERC said was “not useful in determining whether, and under what conditions, to authorize a proposed natural gas transportation project”—or other methodologies. Two FERC commissioners dissented: one commissioner agreed that the project was in the public interest but said FERC needs to “more squarely address” greenhouse gas emissions and the social cost of carbon; the other dissenting commissioner said that FERC’s order on remand failed to provide a “reasoned answer” to the inquiries required by the D.C. Circuit’s August 2017 decision.
    03/07/2018 Order Download FERC's motion to stay issuance of mandate granted. After denying rehearing of its decision ordering additional environmental review of greenhouse gas emissions associated with the Southeast Market Pipelines Project, the D.C. Circuit on March 7 granted FERC’s motion to stay issuance of the mandate. The D.C. Circuit ordered that the mandate be withheld through March 26, 2018. The D.C. Circuit denied the pipeline developer’s motion for a longer stay.
    02/23/2018 Reply Download Reply filed by FERC in support of motion to stay issuance of mandate.
    02/23/2018 Reply Download Reply filed by pipeline project developers in support of motion for 90-day stay of issuance of mandate.
    02/16/2018 Response Download Response filed by petitioners to motions to stay issuance of mandate. The petitioners filed a response opposing the motions for stay of issuance of mandate, arguing that there was not good cause to allow FERC and the developers to use a stay “to skirt the vacatur”; the petitioners also argued that the court should not “pre-judge” whether FERC’s additional environmental review complied with the court’s remand order. In addition, the petitioners argued that there would not be irreparable harm to consumers or to the environment and that economic harm to the developers did not justify delaying the mandate.
    02/06/2018 Motion Download Motion to stay issuance of mandate filed by FERC. FERC and Pipeline Project’s Developers Sought to Delay D.C. Circuit’s Revocation of Project Authorizations. After the D.C. Circuit denied rehearing of its decision requiring additional environmental review of greenhouse gas emissions associated with the Southeast Market Pipelines Project, the Federal Energy Regulatory Commission (FERC) and the project’s developers filed motions to stay issuance of the mandate. In their motions, which were filed on February 6, 2018, FERC sought a 45-day stay, and the developers sought a 90-day stay. FERC stated that it had issued a final supplemental environmental impact statement on February 5 and that it would issue an order in compliance with the court’s mandate within 45 days. In the meantime, FERC argued, a vacatur order by the court would revoke certificates of public convenience and necessity for pipelines currently providing natural gas to Florida power plants, which could potentially endanger the electricity supply to Florida residents.
    02/06/2018 Motion Download Motion filed by pipeline project developers for 90-day stay of issuance of mandate. The developers’ motion to stay issuance of the mandate asserted that FERC had cured the environmental review deficiencies identified by the court (notwithstanding petitioners’ criticisms of the methodologies used by FERC) and that vacatur would cause significant irreparable economic and environmental harms. The developers further argued that it was appropriate to stay the mandate to avoid irreparable harm during preparation of and disposition of a petition for writ of certiorari and that stay of the mandate was warranted even under the traditional test for stay pending appeal. The developers have also asked FERC to expedite reissuance of certificates authorizing the project or to issue temporary emergency certificates.
    01/31/2018 Order Download Panel rehearing denied. D.C. Circuit Denied Rehearing of Decision Vacating Gas Pipeline Approval for Failure to Adequately Consider Greenhouse Gas Emissions. The D.C. Circuit Court of Appeals denied petitions for rehearing of its decision vacating the Federal Energy Regulatory Commission’s (FERC’s) authorization of an interstate natural gas pipeline in the southeastern United States. In August 2017, the D.C. Circuit found that FERC’s analysis of the pipeline’s impacts on greenhouse gas emissions was inadequate and required FERC to prepare a new environmental impact statement. FERC and the respondent-intervenors had argued that remand without vacatur would have been the proper remedy.
    01/31/2018 Order Download Rehearing en banc denied.
    12/04/2017 Reply Download Supplemental reply filed by intervenor-respondents in support of rehearing petition.
    11/28/2017 Response Download Supplemental response filed by petitioners to rehearing petitions.
    11/20/2017 Response Download Opposition filed by petitioners to intervenor-respondents' motion to file reply in support of rehearing petition.
    11/15/2017 Reply Download Reply filed by intervenor-respondents in support of petition for panel or en banc rehearing as to remedy.
    11/15/2017 Reply Download Motion filed by intervenor-respondents to file reply in support of petition for panel rehearing or rehearing en banc.
    11/13/2017 Response Download Response filed by petitioner G.B.A. Associates, LLC in opposition to rehearing petitions.
    11/10/2017 Response Download Response filed by petitioners to rehearing petitions.
    10/17/2017 Opposition Download Opposition to Florida Reliability Coordinating Council, Inc.'s motion for leave to file an amicus brief filed by petitioners.
    10/10/2017 Amicus Brief Download Amicus brief filed by Florida Reliability Coordinating Council, Inc. in support of request for panel rehearing.
    10/06/2017 Petition for Rehearing Download Petition for panel or en banc rehearing filed by intervenor-respondents as to remedy.
    10/06/2017 Petition for Rehearing Download Petition for panel rehearing filed by respondent.
    08/22/2017 Opinion Download Remanded to FERC for preparation of an environmental impact statement. D.C. Circuit Said FERC Needed to Provide More Information on Pipelines’ Downstream Greenhouse Gas Emissions—Or Explain Why It Couldn’t. In a split opinion, the D.C. Circuit Court of Appeals found that the environmental impact statement (EIS) prepared by the Federal Energy Regulatory Commission (FERC) for the Southeast Market Pipelines Project did not contain enough information on the greenhouse gas emissions that would result from combustion of the gas that the project would carry. When completed, the project—which comprises three interstate natural-gas pipelines in the southeastern United States—would be able to carry one billion cubic feet of natural gas per day. The D.C. Circuit concluded that “at a minimum, FERC should have estimated the amount of power-plant carbon emissions that the pipelines will make possible” because it was reasonably foreseeable that the transported gas would be burned in Florida power plants. The court distinguished its conclusion in earlier cases that FERC had no legal authority to consider the environmental effects of natural gas that would be exported from the liquefied natural gas (LNG) facilities it authorized. The D.C. Circuit said that while FERC was forbidden from relying on the environmental effects of gas exports as a justification for denying an upgrade license for an LNG facility, FERC’s authority over pipelines permitted FERC to deny a pipeline certificate on the ground that it would be too harmful to the environment. The D.C. Circuit also was not persuaded by FERC’s “practical objection” regarding the impossibility of knowing “exactly what quantity of greenhouse gases will be emitted as a result of this project being approved.” The court said FERC should have either made a quantitative estimate of downstream greenhouse gas emissions or “explained more specifically” why it could not do so. The court also indicated that the fact that downstream emissions might be offset by reductions elsewhere (from the retirement of coal-fired plants, for example) did not excuse FERC from making emissions estimates. In response to petitioner Sierra Club’s argument that FERC should use the Social Cost of Carbon to convert emissions estimates to concrete harms, the D.C. Circuit directed FERC to explain in the EIS whether it would adopt the position it took in the EIS for an LNG terminal that the Social Cost of Carbon was not useful for purposes of environmental review under the National Environmental Policy Act. In addition to its holdings regarding FERC’s greenhouse gas emissions analysis, the D.C. Circuit also determined as a threshold matter that the petitioners had standing to challenge all three segments of the pipeline project, not just the segment alleged to have caused an injury-in-fact and upheld other aspects of FERC’s environmental review. Judge Janice Rogers Brown dissented on the issue of downstream emissions, writing that in her view such emissions did not need to be considered because FERC did not control whether the greenhouse gas emissions would occur.
    01/31/2017 Brief Download Brief filed by FERC. FERC Said Environmental Review for Gas Pipeline Adequately Assessed Greenhouse Gas Impacts. The Federal Energy Regulatory Commission (FERC) defended its approval of natural gas pipeline projects in the southeastern United States. FERC argued that it satisfied the requirements of the National Environmental Policy Act, including by taking a hard look at potential impacts on climate change. FERC said that it had reasonably determined that the projects would not significantly contribute to greenhouse gas cumulative impacts. FERC’s brief noted that power plants receiving gas from the pipeline projects would be using it to convert from burning coal, thereby reducing those plants’ greenhouse gas emissions and potentially offsetting some regional emissions. FERC rejected the contention that it should have quantified downstream effects using a life-cycle analysis, which FERC had concluded would require it to engage in speculation. FERC said its approach to assessing climate change impacts was consistent with Council on Environmental Quality guidance and with D.C. Circuit precedent.
    12/09/2016 Brief Download Opening brief filed by petitioners. Environmental Groups Said FERC’s Failure to Consider Gas Pipeline’s Downstream Effects Violated NEPA. Sierra Club, Flint Riverkeeper, and Chattahoochee Riverkeeper filed their opening brief in their challenge to the Federal Energy Regulatory Commission’s (FERC’s) authorizations for a natural gas pipeline project extending from Alabama to Florida. One of the petitioners’ three primary arguments was that FERC violated the National Environmental Policy Act (NEPA) and acted arbitrarily and capriciously by not considering the reasonably foreseeable indirect downstream environmental effects of the pipeline project, including “the greenhouse gas, health, and climate effects of burning 1.1 billion cubic feet of natural gas per day for several decades” when tools were available and used by other federal agencies exist to measure such impacts.
    10/24/2016 Motion Download Emergency motion for expedited consideration filed. Groups Asked D.C. Circuit to Expedite Consideration of Challenge to Natural Gas Pipeline. Three environmental groups challenging a natural gas pipeline from Alabama to Florida asked the D.C. Circuit Court of Appeals to expedite consideration of their petition for review. The petitioners said they wished to obtain a ruling on the merits prior to the scheduled May 2017 completion date for the pipeline in the event that the D.C. Circuit did not grant a stay. The petitioners also said that they would still request an expedited schedule if a stay were granted to minimize harm to the other parties. The groups argued that the Federal Energy Regulatory Commission's (FERC’s) determinations were subject to “substantial challenge” and appropriate for expedited review because of FERC’s failure to consider downstream environmental impacts, including greenhouse gas emissions. The groups said FERC’s review was at odds with EPA and Council on Environmental Quality guidance, caselaw, and the NEPA regulations.
    09/20/2016 Petition for Review Download Petition for review filed. Environmental Groups Challenged Natural Gas Pipeline in Southeastern U.S.. Sierra Club, Flint Riverkeeper, and Chattahoochee Riverkeeper filed a petition in the D.C. Circuit Court of Appeals seeking review of Federal Energy Regulatory Commission (FERC) orders authorizing construction and operation of a natural gas pipeline project extending from Alabama to Florida. In a statement, Sierra Club said the petitioners would argue that FERC failed to disclose the pipeline’s climate impacts, including the impacts of power plants supplied by the pipeline. The environmental organizations filed the lawsuit after FERC denied their request for rehearing.
  • In re Florida Southeast Connection, LLC
    Docket number(s): CP14-554-001, CP15-16-001, CP15-17-001
    Court/Admin Entity: FERC
    Case Documents:
    Filing Date Type File Action Taken Summary
    02/02/2018 Request Download Request filed for expedited issuance of order on remand reissuing certificates, or in the alternative, abbreviated application for temporary emergency certificates.
    09/07/2016 Order Download Order issued denying rehearing. The Federal Energy Regulatory Commission (FERC) denied rehearing of its authorizations for construction and operation of a natural gas pipeline from Alabama to Florida. FERC rejected the organizations’ call for consideration of indirect effects related to induced upstream production and downstream natural gas consumption.

© 2023 · Sabin Center for Climate Change Law · U.S. Litigation Chart made in collaboration with Arnold & Porter Kaye Scholer LLP

The materials on this website are intended to provide a general summary of the law and do not constitute legal advice. You should consult with counsel to determine applicable legal requirements in a specific fact situation.